Wyckoff/Mars Hill Rd. 42” Pipeline Replacement

The Cobb County-Marietta Water Authority selected ESI to design the replacement of an an aging water line.


Details:

The existing 42” prestressed concrete cylinder pipe (PCCP) will be replaced with approximately 7,000 LF of 42” zinc-coated ductile iron pipe (DIP) water main. The line will run from the Hugh A. Wyckoff Water Treatment Plant to Highway 41 and connect to an existing main at Mars Hill Church Road.

Mid-South Builders was selected as contractor and will be working with ESI’s Resident Project Representative, Patrick. Work is already under way and expected to be completed early 2020.